PT MRT Terus Lakukan Rangkaian Tes Sistem Kereta
.
photo Rudi Hermawan - Beritajakarta.id

PT MRT Continues to Conduct Series of Train System Tests

The construction of the phase I MRT (Lebak Bulus-HI Roundabout) has reached 97.52 percent. To make it operate in March 2019, the series of tests and inspection of the MRT train system continues to be conducted. 

The construction progress has touched 97.52 percent 

"The construction progress has touched 97.52 percent and the rest of 2.5 percent is just finishing stage such as escalator and entrance," expressed William P Sabandar, President Director of PT MRT Jakarta at Dukuh Atas Station, Central Jakarta, Thursday (11/29).

DPRD Chairman Expects MRT to Operate Soon

Currently his party continues to test out and inspect the system of the MRT train. The system test itself has been ongoing since August 9, 2018.

"Operation is done automatically. This requires a very high level of accuracy," he told.

Thus far, around 12 out of 16 trains have been arrived in the capital. Then other four trains are predicted to arrive by the end of this year.

"We'll test out them for one month in mid-February. It will be officially commercial in March 2019," he stated.

Linked News
Popular News indeks
  1. Jakarta to Go Dark for One Hour on April 26, 2025

    access_time24-04-2025 remove_red_eye1310 personAldi Geri Lumban Tobing
  2. Earth Day in Jakarta Reduces 297 Tons of Carbon Emissions

    access_time27-04-2025 remove_red_eye368 personBudhi Firmansyah Surapati
  3. Pramono Wants to Strengthen Betawi Culture

    access_time26-04-2025 remove_red_eye344 personDessy Suciati
  4. Pramono-Rano Launch New Transjabodetabek Route from Blok M to Alam Sutera

    access_time24-04-2025 remove_red_eye318 personDessy Suciati
  5. Earth Day, Pramono Encourages Citizens to Switch Off Lights Simultaneously

    access_time26-04-2025 remove_red_eye312 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik